New build snagging checklist
A snagging checklist is a room-by-room list of the defects and unfinished work to look for in a newly built home, so the developer can put them right. This one is for UK buyers, professional snagging inspectors and site teams, and covers the outside, every room, the services, the handover papers and how to report what you find.
Last reviewed by ProSurvey Apps Limited
At a glance
- Who it is for
- Buyers of new build houses and flats, professional snagging inspectors, and developers’ site and customer care teams.
- When to use it
- At the pre-completion inspection, in your first days after moving in, and again before the builder’s two-year warranty period ends.
- Time needed
- Allow half a day for a family house and two to three hours for a flat. Writing up a formal report takes longer.
- What to bring
- Phone or tablet for photos, torch, spirit level, tape measure, plug-in socket tester, low-tack tape, and the plans and specification.
Ticks on screen are not saved. Print it, save it as a PDF, or run it in the app with photos.
The snagging checklist
Thirteen sections, in the order most inspectors walk a house: paperwork, outside, then each room, services, loft and handover. Skip what does not apply to a flat.
1.Before you start
2.Outside: walls, roof and chimneys
3.Outside: gutters, drainage and services
4.Outside: grounds, boundaries and outbuildings
5.Doors, windows and glazing
6.Walls, ceilings and decoration
7.Floors, stairs and joinery
8.Kitchen and utility room
9.Bathrooms, en suites and WCs
10.Heating, hot water and ventilation
11.Electrics, alarms and connections
12.Loft and roof space (only where safe to enter)
13.Handover documents and completion day
What is snagging?
Snagging is checking a newly built home for defects and unfinished or poorly finished work, then listing them so the developer puts them right. The list is called a snag list, and each item on it is a snag.
The New Homes Quality Board’s homeowner guide to snagging separates the two words people use. Snags are minor or cosmetic issues that do not affect how the home works or its safety: paint runs, small scratches, scuffed woodwork. Defects are more significant problems that affect how the home functions, such as plumbing or electrical faults. Both go on your list. Anything that affects health or safety should be reported to the developer straight away rather than saved for the list.
When should you snag a new build?
There are three useful moments: the pre-completion inspection before legal completion, your first days living in the home, and a final pass before the builder’s two-year warranty period ends.
| When | What happens | What to use |
|---|---|---|
| Pre-completion inspection | Under the New Homes Quality Code, the developer must let you inspect, or appoint a suitably qualified inspector, after the notice to complete is served and before the completion date. | The NHQB template for the formal record; this checklist to prepare. |
| First days after moving in | Some faults only show once you live there: drainage, heating, draughts, doors that stick. Deadlines for reporting cosmetic damage are often short. | This checklist, room by room, surfaces first. |
| Before the end of year two | Registered developers must run an after-sales service for at least two years from completion. Under NHBC’s Buildmark, the first two years are usually the builder warranty period. | A second full pass with this checklist. |
Part 2 of the New Homes Quality Code says the completion notice period is usually expected to be at least 14 calendar days, so there is time for the inspection. The inspection is not meant to delay completion. Instead, the developer must respond to what it finds, and where issues breach the warranty technical standards the developer is responsible for addressing them, ideally before legal completion or within 30 days if that is not possible.
If your home has NHBC Buildmark cover, NHBC explains that the builder warranty period is usually two years from the start date on your policy certificate, and during that time the builder, not NHBC, is responsible for putting right problems caused by failing to meet NHBC requirements. Other warranty providers set their own terms, so read your policy.
If your developer is registered with the New Homes Quality Board
Version 2 of the Code applies to homes reserved from 2 March 2026; version 1 covers earlier reservations. It says the pre-completion inspection must be carried out and recorded on the Board’s standard Pre-Completion Inspection Checklist, and that a suitably qualified inspector must use only that template. It can be reproduced digitally, but every check on the original template must still be made.
So use the official template for that formal inspection: there is one for a house and one for an apartment. Use this checklist to prepare, to catch the things buyers often forget (keys, meter readings, documents, drainage after rain) and for every snag list after you move in, where the Code does not prescribe a format. If your developer is not registered, check what your reservation agreement, contract and warranty say about inspecting before completion.
How to snag a new build properly
Work in daylight, follow the same route through every room, operate everything that moves or runs, and judge finishes from the distances the industry uses rather than from a few centimetres away.
- Start outside, then work top down inside. Walk the elevations, then go from the loft (only where it is safe and you are allowed) down through each floor to the garage. A fixed route stops rooms being missed.
- Judge finishes from the right distance. The NHQB template’s guidance is to inspect internal walls, ceilings and paintwork in daylight from at least 2 metres without shining a light on the surface, fitted furniture and worktops from 0.5 metres, external walls from at least 10 metres, and glazing from at least 2 metres (3 metres for laminated or toughened glass). A mark you can only find with a torch raking across the wall is unlikely to be accepted.
- Operate everything. Every door, window, lock, tap, flush, switch, socket, extractor, appliance and heating zone. Fill baths and basins to the overflow and watch them drain.
- Measure where there is a tolerance. The template allows spirit levels, plumb lines and tape measures to confirm a stated tolerance, such as a skirting gap of no more than 5mm or at least 25mm between handrail and wall. The aim is to confirm what you can see, not to hunt for faults invasively.
- Mark and record as you go. Low-tack tape on each snag (if the site team agrees) helps the trades find it. Photograph and write up each item there and then, not from memory that evening.
- Record your limitations. Rain, poor light, locked rooms, services not yet connected and areas you could not reach safely all belong in the notes, so nobody assumes they were checked.
What to photograph
Photograph every snag twice: once close enough to show the fault, and once wide enough to show where it is. The NHQB guide recommends taking photos as soon as you notice an issue, because visual evidence helps get it fixed.
- A wide shot that identifies the room and position, then a close-up with a tape measure or ruler in frame for cracks, chips and gaps.
- A spirit level in frame for anything out of level or plumb.
- A short video for leaks, slow drainage, running cisterns and noisy fans.
- Meter readings and serial numbers on completion day, and the keys and fobs you were handed.
- Rating plates on the boiler, heat pump and appliances, which help with any later warranty claim.
- Anything the developer says will be finished later, so you can show it was outstanding at handover.
Caption each photo the way you will describe the snag: room, element, position, fault. For example: “Bedroom 2, window W2, left jamb: sealant missing along lower 300mm.” Consistent captions make a list the site manager can act on without phoning you.
How to report snags to the developer
Send one numbered, written snag list to the developer’s customer care team, with photos, and keep a dated log of every reply.
- One item per line: number, room, element, exact position, what is wrong, photo reference. Order it the way you walked the house.
- Separate emergencies. The NHQB guide treats faulty external door locks, uncontainable water leaks, complete failure of heating and hot water, and total loss of power as emergencies, not snags. Use the developer’s emergency procedure for those.
- Keep a record. NHBC tells Buildmark policyholders to contact the builder as soon as they reasonably can within the builder warranty period, and to keep a record of what they said, who they spoke or wrote to, and when.
What the Code expects of a registered developer
Part 3 of the New Homes Quality Code requires an after-sales service for at least two years from completion. The developer must acknowledge snags as soon as possible and, in most situations, settle an after-sales issue within 30 days unless there is a significant reason for delay. If there is a delay, it must explain why and update you at least once a month.
If snags are not fixed
Make a formal complaint under the developer’s complaints procedure. The Code sets minimum steps: a written acknowledgement within five days, a “path to resolution” letter within 10 days, a complaint assessment and response letter within 30 days, and an eight-week letter by day 56 if the complaint is still open. A complaint that arose within the first two years after completion can be referred to the New Homes Ombudsman Service 56 days after the complaint start date. For NHBC Buildmark homes, NHBC’s resolution service may help once you have been through the builder’s complaints process and have its final written response, or have had no response within 30 days.
Common new build snags, and what usually is not one
Most snags are finishing issues: decoration, sealant, doors, drainage and heating that has not been balanced.
- Paint runs, missed patches, and paint on sockets, glass and floors.
- Shrinkage cracks as the building dries out. The NHQB guide’s rule of thumb is to report cracks wider than a £1 coin.
- Doors that stick, swing open or will not latch; cupboard doors out of line.
- Missing or patchy sealant around baths, showers, worktops and window frames.
- Radiators that stay cold at the top or never warm up; noisy pipework.
- Slow or gurgling drainage, and cisterns that keep running.
- Scratched glass or window frames, and trickle vents that are missing or jammed.
- Gardens that stay waterlogged, paths that hold water, and rubble buried under turf.
- Loft insulation left patchy and ventilation ducts that have come loose.
The NHQB guide lists things that typically do not count: consumables such as bulbs, batteries and tap washers; wear and tear or damage after you move in; problems from your own DIY; small shrinkage cracks; and condensation or mould caused by keeping windows and vents closed. A new home takes time to dry out, so keep it heated and ventilated. Faulty or missing ventilation, though, is a snag.
Running this checklist in PropertySurvey Pro
PropertySurvey Pro runs snagging inspections on iPhone, iPad and Android, works without signal on site, and builds the PDF snag list on the device, so the developer can have it the same day. Photo captions are numbered in the report, and with Pro you can mark up a photo with circles, arrows and labels to point at the exact fault.
You can dictate as you walk, or use “Talk through a room”, which turns a spoken walk-through into entries you then check. AI Polish expands shorthand such as “bed 2 W2 sealant missing low L jamb” into draft wording you review and edit; it never decides whether something is a defect. When the developer says the work is done, start a follow-up visit from the finished survey to re-inspect. The free app runs real surveys, exports PDF reports with the app’s watermark, includes 3 free uses a month of each AI tool and stores up to 25 surveys on the device. Pro (£19.99 a month or £199.99 a year) adds cloud sync, your own branding and the full AI allowance. See pricing for the detail.
Snagging checklist: frequently asked questions
What is a snagging checklist?
A snagging checklist is a list of checks for a newly built home, used to find defects and unfinished work so the developer can put them right. A complete one covers the outside, every room, the heating, plumbing and electrics, the documents handed over at completion, and how to photograph and report each snag.
When should I do a snagging inspection on a new build?
Snag at the pre-completion inspection, after the notice to complete is served and before legal completion, then again in your first days in the home, and once more before the builder’s two-year warranty period ends. For homes covered by the New Homes Quality Code, the formal pre-completion inspection is recorded on the New Homes Quality Board’s template checklist.
Can I do my own snagging inspection?
Yes. The New Homes Quality Code lets buyers either do the pre-completion inspection themselves or appoint a suitably qualified inspector. The Code says developers must tell buyers that the template was designed for professionals, so a buyer may miss or interpret some standards differently. An inspector must belong to a recognised professional body, hold professional indemnity insurance and work within their competency.
How long do I have to report snags on a new build?
Report snags as soon as you find them. The New Homes Quality Code requires registered developers to provide an after-sales service for at least two years from completion, and under NHBC’s Buildmark the builder warranty period is usually two years from the policy start date. Developers often set much shorter deadlines for reporting cosmetic damage such as scratches, so check surfaces first.
What is the difference between a snag and a defect?
The New Homes Quality Board describes snags as minor or cosmetic issues that do not affect how the home works or its safety, such as paint runs or small scratches. Defects are more significant problems that affect how the home functions, such as plumbing or electrical faults. Report both, and report anything affecting health or safety to the developer straight away.
Is condensation or mould in a new build a snag?
It depends on the cause. The New Homes Quality Board’s homeowner guide says problems caused by inadequate ventilation, such as keeping windows and vents closed, do not usually count as snags. Missing or faulty ventilation is different: a trickle vent that will not open, an extractor fan that does not run or loose ducting in the loft belongs on the snag list.
Do I still need a snagging inspection if my home has a 10-year warranty?
Yes. A new home warranty does not replace snagging. Under NHBC’s Buildmark, for example, the builder is responsible for putting right problems caused by not meeting NHBC requirements during the first two years, and cover after that is insurance for damage caused by defects in certain parts of the home. Finishing snags need to be found and reported early.